| THE TILLY FOSTER ENERGY PROJECT |
|
THE TILLY FOSTER SOLAR POWER PROJECT Tilly Foster Farm & Conservation Area is
199 acres of a scenic complex of pastures and historic farm
buildings located at 100 Route 312, The impetus for the installation for
solar power system at the farm came from the members of the
Tilly Foster Advisory Board. Installing a solar power system at
Tilly Foster Farm was consistent with the vision to evolve Tilly
Foster Farm into an education farm for the public and an
opportunity for It is always a challenge for
municipalities like
While the New York State Energy Research
and Development Authority (NYSERDA) has ongoing incentives for
the installation of photovoltaic (PV) systems, a unique 1.3
million dollar funding opportunity became available under
Program Opportunity Notice (PON) 969. Funding for the project
was from a settlement of a lawsuit by the New York State
Attorney General against the Ohio Edison Company. This program
was earmarked for the installation of solar power systems
exclusively on The submission of the grant was a joint
effort, by The maximum reimbursement from NYSERDA
for this project was $84,500 which offset approximately 80% of
the cost of the project. As a recipient of the grant This substantial grant funding from
NYSERDA was critical in the decision for
Once the funding was in place design
consultant John Calhoun, PE developed a preliminary design
and prepared project specifications based on the farm's
electricity use patterns and the physical layout. The horse barn, which contains the Power
Conditioning System (PCS) equipment, is located at the main
entrance to the Tilly Foster Farm and Conservation Area along
with several offices, educational and support buildings.
The utility electric service is distributed throughout the
campus from the 120/240VAC, 200A service entrance in the barn.
A storage room in the barn will be dedicated to the PCS
equipment and interpretive items related to the PV system.
It is adjacent to the main electrical room, allowing simple
conduit routing to the interconnect point. Electricity from the PV system partially
displaces purchases of utility power to the cluster of buildings
located off the main entrance at the Tilly Foster Farm and
Conservation Area . The PV array was placed in an open
field approximately 700 feet from the barn in an area with no
obstructions and no shade. The array faces south at an
optimum 40 degree tilt. The ground-mounted array and its
interpretive display border a primary hiking and skiing trail
for easy public access. Conductors from the array to the
PCS are installed in an underground along this trail.
In February 2008 the Purchasing
Department issued an RFP for a NYSERDA approved, photovoltaic
(PV) system contractor to install a 13kW, grid-connected PV
system. After an extensive evaluation process, the
contract was awarded to:
The project began in July 2008. Hudson
Valley Clean Energy worked closely with Hudson Valley Clean Energy installed a
Sun Power 225 Solar Panel. The PV system consists of 56 225 Watt
solar modules mounted on 7 poles. The PV system interconnects
with the NYSEG utility grid. The 13,000W array consists of fifty six
225W solar modules.. The PV modules are ground-mounted on a
commercial rack with concrete footings. The structure is
approximately 11 feet high and 70 feet wide. Conversion
of the PV array's DC output to 240VAC and automatic control of
system operation is accomplished with two 6000W and one 2500W The installation was completed in August
2008. The final NYSEG inspection was completed in fall and
the system went live October 2, 2008. Under typical weather conditions the
13kW PV system should produce 15,840kWh per year, 33% of the
building's annual electrical consumption based on the 2005
billing history. Prior to installing installation of the
net meter we have saved approximately $2,000.00. Attachments: Diagram of
Photovoltaic Generating System Net metering is a policy that allows
owners to receive the full value of the electricity that their
solar energy system produces. Net metering offsets the electric
bill with any excess electricity they produce because if more
electricity is produced from the PV system than required the
extra kilowatts are fed back into the utility and the meter runs
backwards. In February of 2009 municipalities in
Education and Outreach Plan One of the main goals of PON 969 was to foster a market for PV systems and to provide the public with an opportunity to learn about PV systems. Tilly Foster Farm & Conservation Area is open to the public every day of the year and the installation of a PV System is consistent with the vision to evolve Tilly Foster Farm into an educational farm for the public To foster education on the use of PV
energy we have an on-site informational Bulletin Board with a
digital output meter and are in the final stages of installing
an additional informational Kiosk. To ensure that all local residents,
businesses, school officials are well informed on the PV
system we have NYSERDA informational brochures for distribution
at Tilly Foster Farm & Conservation Area , the Putnam County
Office Building and at other County owned facilities. In October 2008 Preserve Putnam hosted a
Livable Communities which highlighted the Solar Power system at
Tilly Foster Farm.
LINKS TO OTHER SOURCES OF INFORMATION: For additional information on solar
energy visit the following sites: To learn about alternative energy sources and incentives and funding opportunities please visit: While the return on the investment is
not immediate, |
|
||
WWW.PUTNAMCOUNTYNY.COM 2010 ALL RIGHTS RESERVED |
